Maintenance Plans now follow the actual completion of the previous Work Order, not a fixed calendar. Fewer unnecessary Work Orders, and your backlog stays clean.
Before: a monthly Work Order is finished three weeks late. The next one is still due on its next calendar date.
Now with After completion: the next due date counts from the real completion date. Finished three weeks late? The next Work Order is due a month after that.
Also improved: all scheduling options are clear at a glance. And the lead time adjusts automatically to your repetition interval. Two weeks in advance means exactly that.